An existing access road linking Long Banga Junction to Pa Dalih (Section B), in the Miri Division is being improved in an infrastructure project implemented by the Highland Development Agency (HDA), under RECODA.
The current access road will be upgraded to a 29.2km gravel road of R1 Standard. The site has been cleared for construction while soil investigation works have been completed.
Land aquisition and right-of-way (ROW) survey by the Miri Land & Survey Department is ongoing. The existing access road is maintained to ensure continuous vehicular traffic movement with installation of temporary road signs and devices in place.
Construction workers have been instructed adhere to the SOP set by health authorities, especially during the Conditional Movement Control Order (CMCO) period. The project, which began last year, is expected to be completed by 2022.