A new 8km road linking Nanga Belawai to Rumah Jabang, in Ulu Belawai, in the Kapit district is being constructed in an infrastructure project implemented by the Upper Rajang Development Agency (URDA), under RECODA.
The project, which is expected to be completed by the end of this year, will see the construction of a R1 Standard road with a spur road linking to SK. Nanga Terusa.
Soil investigation works have been completed, while earthworks and culvert works are ongoing. Encasement casting for the concrete culverts has also begun.
Construction workers have been instructed adhere to the SOP set by health authorities, especially during the Conditional Movement Control Order (CMCO) period.
Related posts
Tanjung Manis now a hub for major industries
KUCHING (March 15): Tanjung Manis in Sarikei has moved on well from being a timber industry hub since [...]
Read moreInternal roads improved in Long Lama town
The residents of Long Lama town now have access to a smoother and improved internal road due to the [...]
Read moreConstruction of proposed new road from Kpg Noor Islam to Kuala Lawas ferry point in progress
A new 3.07km road is under construction linking the coastal village of Kampung Noor Islam to Kuala [...]
Read moreUTS, Press Metal Bintulu ink MoU to renew partnership
SIBU (Feb 25): University of Technology Sarawak (UTS) and Press Metal Bintulu Sdn Bhd (PMB) signed a [...]
Read more