The upgrading works on the 29.2km existing gravel road from Long Banga junction to Pa Dalih (Section B) is in progress. The improvement of the road to R1 JKR standard road implemented by Highland Development Agency (HDA), under RECODA is expected to be completed towards the second quarter of this year.

Currently ongoing at the site is the laying of the road sub base, as well as the compound sealing works on the concrete road pavements. Improved drainage along the roads is also being installed.