A kick-off meeting for the access road project to Tunoh in Kapit was held earlier this morning and chaired by our Project Management Director, Mohd. Safri Ibrahim.

The meeting, attended by consultants among others, discussed and deliberated on the conceptual design for the construction of this 38km road of JKR R1 standard from Baleh Dam Access Road at Nanga Sepungil to Tunoh.

This proposed project will provide a vital road linkage to Tunoh which has been earmarked to be a new township in the near future.

Other than the road construction, the project also involves the construction of six reinforced concrete bridges over Sg. Merirai, Sg. Sebayak, Sg. Lubok, Sg. Telial, Sg. Entuloh and tributary of Sg. Entuloh, drainage works, geotechnical works, road furniture installation and pavement markings and relocation of existing utility services.