Bored piling works for a 130-metre bridge in Nanga Machan, in the Kanowit District, has been completed.
The reinforced concrete bridge will be connected to the 9.5km Ulu Machan road, which is being upgraded to a two-lane R1 standard road.
With the fabrication of reinforcement cages for I-Girders and concreting for the bridge near completion, construction of the embankment slab will begin next month.
Meanwhile, premix laying works for the road is expected to commence within a week.
Construction for both the road and the bridge is expected to be completed by year’s end.
The projects are implemented by the Upper Rajang Development Agency (URDA), under RECODA.
Related posts
Day 2 | Working Visit to Norway
The Sarawak delegation had the opportunity to learn from Mr Hans-Jacob Roald, a renowned Norwegian [...]
Read moreDay 1 | Working Visit to Norway
The official visit started with a briefing session with the City Government of Oslo, providing [...]
Read moreDriving Socio-Economic Growth: RECODA Monitors IPR-INTAN Initiative in Lawas
RECODA’s Socio-Economic Development Unit recently hosted a productive briefing and site visit at [...]
Read moreBoosting Livelihoods: RECODA Supports Lawas Fishermen Through IPR-BMT Initiative
RECODA’s Socio-Economic Development Unit successfully held a handover ceremony for Inisiatif [...]
Read more