Bored piling works for a 130-metre bridge in Nanga Machan, in the Kanowit District, has been completed.
The reinforced concrete bridge will be connected to the 9.5km Ulu Machan road, which is being upgraded to a two-lane R1 standard road.
With the fabrication of reinforcement cages for I-Girders and concreting for the bridge near completion, construction of the embankment slab will begin next month.
Meanwhile, premix laying works for the road is expected to commence within a week.
Construction for both the road and the bridge is expected to be completed by year’s end.
The projects are implemented by the Upper Rajang Development Agency (URDA), under RECODA.
Related posts
Memorandum of Understanding with JPK
A Memorandum of Understanding (MOU) was signed between us and Department of Skills Development this [...]
Read moreCourtesy visit from the Royal Institution of Surveyors Malaysia
We received a courtesy visit from the Royal Institution of Surveyors Malaysia (RISM), led by its [...]
Read moreRepair and improvement of four schools in Bukit Kota, Limbang
Renovation and improvement works are ongoing on four of the dilapidated rural schools in Bukit Kota, [...]
Read moreSamalaju site of SEA’s first integrated low carbon-silicon based materials factory
KUCHING (March 16): The first integrated low carbon-silicon based materials factory in South East [...]
Read more